During stress testing of new locks for the Panama Canal, water
seepage was detected in a specific area of the new Pacific Ocean-side locks in a
section that separates the middle chamber and lower chamber, the Panama Canal Authority
revealed Sept. 7.
This development means that the opening of the canal expansion,
which has had a handful of delays already and is currently planned for spring 2016,
could be pushed back again.
The Panama Canal Authority said it is now awaiting a formal report
from the construction contractor, which will be issued following detailed
inspections. The report is expected to include a root cause analysis, as well as
the recommended repair methodology.
Upon evaluating the report's findings, the Canal Authority says,
it will assess and communicate if the project’s completion timeline will be affected
in any way.
The Authority also says it has designated two independent external
structural engineers to conduct an objective evaluation of the reasons for seepage
and assess the construction contractor’s solution.
Despite the setback, the expansion project has now reached 93
percent completion and work continues in other areas of the project, according to
the Authority. Updates are expected to be issued by the Canal Authority as information
becomes available.
The $5 billion Panama Canal expansion, which is expected to allow
post-Panamax ships to travel through the canal en route to East Coast terminals,
thereby bypassing the US West Coast, was initially scheduled to be completed in
2014 to coincide with the 100-year anniversary of the opening of the existing canal,
but snafus have delayed the completion by nearly two years so far.